Timeline: 2026-06-07 22:20 → 22:40

Table of Contents

Summary

  • 2 opened; 2 story change(s); 2 task change(s); 1 capture(s).

Stories

Tasks

Task Event Notes
Display and manage the ores-shell script library in the Qt UI BACKLOG → STARTED  
Add timeline view to the agile board BACKLOG → STARTED → DONE  

Captures

Pull requests

PR Event Title
#1181 opened [ores.qt] Add the shell script library panel
#1182 opened [modeling] Split MASD docs into pure methodology and applied sets

Problems and suspicious decisions

  • None observed.

Audit

  • Auto-generated bucket; environment stamps unavailable.

Emacs 29.1 (Org mode 9.6.6)