Story: Sprint 26 closure: story cleanup and reset for sprint 27

Table of Contents

This page documents a story in Sprint 26. It captures the goal, current status, acceptance criteria, and the tasks that compose it.

1. Goal

Own the final steps of sprint 26: the close health review, a cleanup that leaves no half-finished story for sprint 27, the release notes and the retrospective.

2. Status

Field Value
State DONE
Parent sprint Sprint 26
Now Nothing.
Waiting on Nothing.
Next Nothing.
Last touched 2026-10-05

3. Acceptance

  • Every other sprint 26 story is DONE or ABANDONED, and compass sprint audit is clean.
  • Release notes are generated and linked from the sprint's Status table.
  • The sprint's Retrospective section is filled.

4. Tasks

Task State Start End Description
Clean up the sprint 26 stories for close DONE 2026-10-05 2026-10-05 Close every finished story, rework and split the eleven that delivered part of their scope, carry the nineteen unfinished stories to the product backlog inbox, and clear every closed document's Now field.
Write sprint 26 release notes DONE 2026-10-05 2026-10-05 Generate the sprint 26 release notes from the merged PR data, fill the summary blurbs, render the charts and export the markdown for the draft GitHub release.

5. Decisions

6. Out of scope

7. Result

Sprint 26 is closed out. Health review 1 rated the sprint RED. Every other story is DONE or ABANDONED, and compass sprint audit is clean. Eleven stories were reworked at the sprint close to the scope they actually delivered and closed DONE, each with its remainder split to a successor story in the product backlog inbox; nineteen unfinished stories were carried to the inbox by file move, and the sprint table records each as ABANDONED at the close date. The release notes, the charts over the full sprint and the retrospective are written. The v0.0.26 tag and the draft GitHub release follow the merge.