Story: Fix the site build id link

Table of Contents

This page documents a story in Sprint 28. It captures the goal, current status, acceptance criteria, and the tasks that compose it.

1. Goal

The site build fails on an uppercase id link to a page that defines its id in lowercase.

2. Status

Field Value
State DONE
Parent sprint Sprint 28
Now Nothing.
Waiting on Nothing.
Next Nothing.
Last touched 2026-10-20

3. Acceptance

4. Tasks

Task State Start End Description
Scaffold story: Fix the site build id link DONE 2026-10-20 2026-10-21 Story scaffolding rides this task: documents, sprint wiring, and the scaffold PR. Close it before merging that PR.
Implement Fix the site build id link DONE   2026-10-21 Initial task for: Fix the site build id link

5. Decisions

6. Out of scope

7. Result

The site build passes. The create-a-report prototype defines its id in uppercase.

Emacs 29.3 (Org mode 9.6.15)