Story: Atomise every convention onto the central entity — the remaining work

Table of Contents

This page documents a story in Sprint 29, carried unfinished from Sprint 28 at close. It captures the goal, current status, acceptance criteria, and the tasks that compose it.

1. Goal

Tenor basis swap is rebuilt on the central convention row and the composite parent-and-parts pattern, with the family get and put generated. Each remaining convention follows in its own PR, and no convention type or row holds the whole convention.

2. Status

Field Value
State DONE
Parent sprint Sprint 29
Now Nothing.
Waiting on Nothing.
Next Nothing.
Last touched 2026-11-08

3. Acceptance

The story closes on the tasks it finished:

  • Let the convention publish parse.

4. Tasks

Task State Start End Description
Let the convention publish parse DONE 2026-10-30 2026-10-30 Task for: Atomise every convention onto the central entity — the remaining work

5. Decisions

6. Out of scope

Emacs 29.3 (Org mode 9.6.15)