Story: Complete a structure from a screen

Table of Contents

This page documents a story in Sprint 29. It captures the goal, current status, acceptance criteria, and the tasks that compose it.

1. Goal

(Describe the user-visible outcome this story delivers.)

2. Status

Field Value
State DONE
Parent sprint Sprint 29
Now Nothing.
Waiting on Nothing.
Next Nothing.
Last touched 2026-11-08

3. Acceptance

The story closes on the tasks it finished:

  • Point the grouping screen at the completion.

4. Tasks

Task State Start End Description
Point the grouping screen at the completion DONE 2026-11-01 2026-11-01 Replace the route's structure-then-members loop with one call to the completion, so grouping a set of trades makes one structure whose every leg is live and waiting.

5. Decisions