1. Goal
Sprint 30 is open: it is the current sprint in the version manifest and the agile index, and the project is on version 0.0.30 with the latest vcpkg.
2. Status
| Field | Value |
|---|---|
| State | DONE |
| Parent sprint | Sprint 30 |
| Now | Nothing. |
| Waiting on | Nothing. |
| Next | Nothing. |
| Last touched | 2026-11-08 |
3. Acceptance
- Sprint 30 is the current sprint in the version manifest and the agile index.
- The project version is 0.0.30.
- The vcpkg submodule is at the latest commit of its tracked branch.
4. Tasks
| Task | State | Start | End | Description |
|---|---|---|---|---|
| Task: Open sprint 30 | DONE | 2026-11-08 | 2026-11-08 | Scaffold and wire sprint 30, bump the version and update vcpkg. |
| Carry the sprint 29 work and review it | DONE | 2026-11-08 | 2026-11-08 | Move the work left from sprint 29 into sprint 30, then check each story against the code. |
5. Decisions
6. Out of scope
- Promoting captures into stories. Sprint planning does that.