Story: Run a report end to end on a synthetic bond population — the remaining work
Table of Contents
This page documents a story in Sprint 30, carried unfinished from Sprint 28 at close. It captures the goal, current status, acceptance criteria, and the tasks that compose it.
1. Goal
One run of the NPV report of ACME Corporation HK Ltd goes from the trigger to a completed report instance with an output archive in storage, and every issue met on the way is written down with its cause and its fix or its owner.
2. Status
| Field | Value |
|---|---|
| State | BACKLOG |
| Parent sprint | Sprint 30 |
| Now | Not yet started. Split from Run a report end to end on a synthetic bond population, which closed in sprint 28 with its done tasks. |
| Waiting on | Nothing. |
| Next | Triage into a sprint. |
| Last touched | 2026-11-08 |
3. Acceptance
- The NPV report of ACME Corporation HK Ltd completes on its 8 synthetic bonds.
- Each issue met is recorded with its symptom, cause and state: fixed, open or handed on.
- Each fix has a test or a re-run that proves it.
4. Tasks
| Task | State | Start | End | Description |
|---|---|---|---|---|
| Show a report run in the grid | BACKLOG | The grid views must show the jobs a report run sends to the grid, to every account that may watch it. |
5. Decisions
- Split from Run a report end to end on a synthetic bond population on 2026-10-24 at sprint 28 close. The acceptance above is copied from that story; its done tasks are recorded there.