Task: Health review 1 — sprint 21 close analysis

Table of Contents

This page documents a task in the Sprint health review — System 2 analysis story. It captures the goal, current status, acceptance, and any notes or results.

Goal

Write a System 2 close analysis for sprint 21, covering goal alignment, sprint load, PR velocity, story/task balance, and focus signal. File the full review in this task's Result section and add a summary row to sprint.org.

Status

Field Value
State DONE
Parent story Sprint health review — System 2 analysis
Now Complete.
Waiting on Nothing.
Next Nothing.
Last touched 2026-06-29

Acceptance

  • Full System 2 review written into Result section with RAG verdicts for each dimension.
  • Summary row added to sprint.org * Health Review table.

Plan

Run compass sprint audit, read sprint.org and all story files, gather git commit load and PR velocity, then produce the structured review.

Notes

Data sources: compass sprint audit output, sprint.org Stories table, story.org State/Now fields per story directory, git log --oneline --since=2026-06-12, gh pr list --state merged --search "merged:>=2026-06-12".

Stale branches flagged by user: feature/db-write-integration (PR #1337, merged 2026-06-26) and feature/compass-env-provision-vcpkg-and-fleet-type (PR #1292, merged 2026-06-24). Both need deletion.

PRs

PR Title
   

Review

# Comment summary File Decision Notes
1 sprint.org #+updated and Last touched stale (2026-06-25/2026-06-12) sprint.org Fixed Bumped to 2026-06-29 in 30ead165e
2 Timeline #+todo: captured as agent name timeline snapshot Deferred Compass tool bug; captured as follow-up
3 task_migrate-party_type #+blocked_on: empty task_migrate-party_type-unified-model.org Fixed Set to FA93094D in 30ead165e
4 sprint_health_review/story.org Out of scope placeholder story.org Fixed Placeholder filled in 30ead165e
5 task_health_review_1.org #+pr: empty task_health_review_1.org Fixed Set to 1371 in 30ead165e
6 codegen-unification-blockers/story.org #+updated stale story.org Fixed Bumped to 2026-06-29 in 30ead165e

Result

Review on 2026-06-29 (day 17 of planned 7 — sprint overdue by 10 days)

Pre-analysis concerns

Before collecting evidence, three concerns stood out that the data might mask:

  1. Sprint 21 had a hard constraint ("no new tooling stories unless they directly unblock a commission task"). Was it respected?
  2. Sprint 21 was planned for 7 days (end 2026-06-19) but is still running on day 17 — has the team been measuring against an honest deadline?
  3. The Accumulate face dataset story has been STARTED since sprint 20 (started 2026-06-10). Is it still actively moving or quietly stalled?

Goal alignment

Sprint mission: "Commission the ores.refdata entity library: finish currency and country, and start the twelve entities that were never touched in sprint 20 — with the hard constraint that no new tooling stories enter the sprint unless they directly unblock a commission task."

Goal Coverage Stories Verdict
Finish Commission: currency Partial STARTED, 14/18 tasks done AMBER — still open, auxiliary codegen synced but currency-entity C++ sync and Wt/HTTP captures remain
Finish Commission: country Partial STARTED, 13/17 tasks done AMBER — SQL, CLI, shell done; C++ core/messaging/Qt codegen tasks remain
Start 12 new Commission entities Minimal party_type (5/11), party_status (3/11), book_status (4/11) STARTED; 9 entities still BACKLOG with no tasks RED — only 3 of 12 touched; 9 entities untouched
Hard constraint: no new non-commission stories Violated Market data approach analysis (DONE), PoC: FX spot (STARTED, 8/9 done), Accumulate face dataset (STARTED, carried from sprint 20) RED — at least 3 stories entered without a direct commission unblock justification

Challenge: "Resolve codegen unification blockers" is a tooling story but its purpose is to unblock the party_type unified-model migration, which is a commission task. It sits on the borderline of the constraint.

The market data workstream (approach analysis + PoC FX spot) consumed substantial capacity and delivered real output — but neither story serves the sprint mission. The face dataset has occupied a STARTED slot since sprint 20 with no mission connection.

Goal alignment verdict: RED — the core commission goal was barely advanced (only 3 of 12 new entities touched, neither currency nor country closed) and the hard constraint was violated by at least 3 unrelated stories.

Sprint load

Metric Value Target Status
Commits since sprint start (2026-06-12) 466 ≤ 300 RED
Elapsed days 17 7 RED — 143% overrun
Commits/day average 27.4 ≤ 43 (300/7) GREEN for rate
PRs merged 99

The commit count and elapsed time are both well beyond target, but the per-day commit rate is not unsustainable — the overrun is driven by sprint duration, not a burst that would collapse. The sprint has simply not been closed. 466 commits is RED against the ≤300 threshold; the planned 7-day window would have been ~191 commits by June 19.

Challenge: a sprint that runs 17 days instead of 7 is not a sprint — it is a mini-iteration. The backlog of commission work that didn't ship is invisible if the sprint is never closed.

Sprint load verdict: RED (466 vs 300; sprint overdue by 10 days).

PR velocity

Metric Value Notes
Total PRs merged 99 2026-06-12 to 2026-06-29
Average PRs/day 5.8 Healthy overall
Burst: 2026-06-25–26 51 PRs in 2 days 52% of sprint PRs in 2 days — WIP release, not steady flow
Quiet window: 2026-06-12–24 ~20 PRs in 12 days 1.7 PRs/day — well below target rate
Currently open PRs 2 (#1356, #1369) Both have recent activity
Stale branches (merged PR, branch not deleted) 2 feature/db-write-integration (PR #1337, merged June 26), feature/compass-env-provision-vcpkg-and-fleet-type (PR #1292, merged June 24)

The overall PR rate is high but masks a problematic distribution: the sprint was effectively idle for its first 12 days (sprint was opened, then not much happened until June 25). The June 25–26 burst suggests a large batch of WIP was resolved simultaneously rather than a steady stream of small deliveries. Both stale branches need cleanup.

PR velocity verdict: AMBER — overall rate is healthy but the early stall pattern and late burst indicate WIP accumulation, not continuous flow. Two stale branches need deletion.

Story and task balance

Stories confirmed STARTED (from story files, not sprint table):

Story State (story file) Sprint table Tasks done/total Days open Notes
Commission: currency STARTED BACKLOG 14/18 17+ Sprint table stale
Commission: country STARTED BACKLOG 13/17 17+ Sprint table stale
Commission: party_type STARTED BACKLOG 5/11 ~4 Sprint table stale
Commission: party_status STARTED BACKLOG 3/11 ~4 Sprint table stale
Commission: book_status STARTED STARTED (sprint table) 4/11 ~4 Sprint table stale
Resolve codegen unification blockers STARTED STARTED 4/10 2 B1 stalled (PR merged, task open)
PoC: FX spot STARTED STARTED 8/9 4 Nearly done
Accumulate face dataset STARTED STARTED 4/5 19 Started sprint 20, still open
Upgrade Qt STARTED BACKLOG 0/2 ~4 Sprint table stale; scaffold task only
Compass env improvements DONE (story file) STARTED Sprint table stale — needs sync to DONE
Market data approach analysis DONE (story file) STARTED Sprint table stale — needs sync to DONE

Sprint table drift: 8 stories have incorrect state in sprint.org vs their story file.

Five BACKLOG stories in the sprint table are actually STARTED in story files (currency, country, party_type, party_status, Qt upgrade). Two STARTED entries in the sprint table are actually DONE (Compass env improvements, Market data approach analysis).

DONE ratio: 9 DONE (sprint table) / ~43 total stories = 0.21 — below the 0.3 RED threshold. But this is distorted by the large pool of BACKLOG Commission/codegen stories that are multi-sprint placeholders. Against worked stories only (DONE + confirmed STARTED = ~20), the ratio is ~0.45 — borderline AMBER.

Challenge: the Accumulate face dataset story has been STARTED for 19 days across two sprints. At 4/5 tasks done it is nearly finished — it needs closing, not carrying into a third sprint.

Story/task balance verdict: AMBER — all STARTED stories are decomposed (good), but sprint table drift is severe (8 stories), and one long-running story (face dataset) needs immediate close-out.

Focus signal

Metric Value Verdict
Simultaneously STARTED stories (story files) 9 RED (≥6 = RED)
Themes covered commission (5), codegen/tooling (1), market data PoC (1), face dataset (1), Qt upgrade (1) Divergent
Stories unrelated to sprint mission 3 market data approach analysis, PoC FX spot, face dataset

Nine simultaneously in-flight stories from five distinct themes violates the sprint's own constraint. The commission theme (5 stories) is coherent but even within it, simultaneous work on 5 entities means none close quickly. The three off-mission stories consumed roughly equivalent capacity to what was needed to close currency and country.

Focus signal verdict: RED — 9 STARTED stories, themes divergent, hard constraint violated.

Overall verdict

Dimension Verdict
Goal alignment RED
Sprint load RED
PR velocity AMBER
Story/task balance AMBER
Focus signal RED
Overall RED

Sprint 21 is RED. Three of five dimensions are RED, and the two AMBER dimensions are both drifting toward RED (the story table has 8 stale entries; PR distribution was badly front-loaded). The sprint ran 17 days against a 7-day plan, produced 466 commits against a 300 target, and ended with neither currency nor country fully commissioned — the two explicit goals. The primary cause is focus fragmentation: the market data workstream (approach analysis + PoC FX spot) was injected mid-sprint without a commission-unblock justification, consuming substantial capacity and setting a precedent that made the hard constraint meaningless. The single most important corrective action for sprint 22 is to enforce the sprint constraint at story injection time, not retrospectively: if a story does not directly serve the sprint mission, it does not enter the sprint table.