Story: Open sprint 29 — the remaining work

Table of Contents

This page documents a story in Sprint 30, carried unfinished from Sprint 29 at close. It captures the goal, current status, acceptance criteria, and the tasks that compose it.

1. Goal

(Describe the user-visible outcome this story delivers.)

2. Status

Field Value
State ABANDONED
Parent sprint Sprint 30
Now Nothing.
Waiting on Nothing.
Next Nothing.
Last touched 2026-11-08

3. Acceptance

4. Tasks

Task State Start End Description
Get v0.0.29 up and running ABANDONED 2026-10-24 2026-11-08 After the sprint 29 opening, bring v0.0.29 up on a fresh environment. The ORE provider must not show in the web client, and the feeds screen must show the feeds that run.

5. Decisions

  • Split from Open sprint 29 on 2026-11-08 at sprint 29 close. The acceptance above is copied from that story; its done tasks are recorded there.
  • Sprint 29 is closed, and this story has no goal of its own. (review at sprint 30 start, 2026-11-08.)

6. Out of scope

Emacs 29.3 (Org mode 9.6.15)